With the continued efforts of ANR Construction Ltd. crews, the City Hall construction site has been quite busy since our last update. Both exterior and interior work has been advancing nicely including:
- Installation of frames and glass in windows
- Complete siding on west and north walls
- HVAC, Drywall installation ongoing
- Sprinkler system in basement complete
- Plumbing on test
- Spray foam gables/truss ends
- Generally complete framing
- HVAC/pipe insulators on site