The sounds of progress have been rippling through town as ANR Construction Ltd. crews completed preparations for sidewalks and parking lots. Interior work is still moving smoothly including:
- waterproofing roof and sheathing
- plumbers onsite
- tree removal on Bridge St
- framing full height of walls, main floor continued
- drywall basement
- parking lot and sidewalk preparations
To view current and past progress reports, visit the city hall webpage.